The following things are known issues with the MPX export feature:
  • When exporting to MS Project 2007, the MPX import has to be explicitly allowed in the MS Project settings
  • When exporting to MS Project 2007, Project by default imports the MPX file twice click "Cancel" the second time)
  • There is apparently no way to import "Work" (in hours or days), but only "Duration"

A workaround for this, in a later version, would be making use of the MS Project 2007 XML import possibilities.